Dam Design

Participation Energoproekt AD development and construction of dams

Subject of the Contract Investor Period
1 "Reconstruction and extension of port terminal "Lesport" – construction of a protective wall for the defence of the reclamation areas from the influence of the waves of Varna Lake; the stability of the slopes of the protective walls is managed with a mound made of quarry run material "Port Lesport" AD 2010 - 2011
2 Work design: Defence of the town of Vidin – section "Baba Vida" Vidin Municipality 2003г.
3 Technical assistance for the site "Construction of a grouting curtain to the side of the diversion tunnel of Asarelska River up to the basin for rich solutions" and the site "Construction of a curtain grouting in two rows to Asarelska River with the use of drill wells and construction of a protective mole from the upper side of the drill wells" "Omikron" AD 2001г.-2002г.
4 Gorna Arda Hydropower Project – Water Power System (WPS) "Sarnitsa" design preparation NEK 2001 - 2002
5 Designer supervision, participation in inspection boards of site: Irrigation Installation "Ogosta". "Ogosta" Dam. Reinforcement of a landslide – left slope. "Agrovodinvest" EAD 2001г.-2002г.
6 Periodical measurements of the deformations of the excavation contour of tunnel 1 (calotte and bench) and tunnel 2 (calotte and bench) of WPS "Madan" "Stanilov" EOOD 2001г.
7 "Work design for the reinforcement of counter-wall "Rozov Kladenec" and "Soil Design" NEK - EAD - Enterprise "Dams and cascades" 2001г.
8 Pre-design study under article 66 of the Water Law for a small HPP "Yugovska 2" for the utilization of the hydro-energetic potential of Yugovska River between bench marks 505,00 and 482,00 "Trakia Shtrom" OOD 2001г.- 4 месеца
9 Gorna Arda hydropower project - WPS "Madan" – Preparatory construction works on dam wall "Madan" - and HPP "Byal Izvor" – execution of periodical designer's supervision and preparation of the related technical documentation NEK 2001г.
10 Survey and Design Works for the site "Reinforcement of the banks of Arda River in the area of the town of Kardzhali" Ministry of Regional Development and Public Works (MRDPW) 08.06.2000г.
11 Work design for the site Yadenitsa dam – correction of Yadenitsa River in pursuance of section 6 from the Decisions of the Ministry of Environment and Waters concerning the Environmental Impact Assessment NEK - AD, branch "Hidroelektroinvest" 2000г.
12 Increasing of the volume of the lower leveller of Pumped-storage HPP "Chaira" with construction of Yadenitsa dam – WPS Yadenitsa NEK 1999г.- 2001г.
13 Gorna Arda hydropower project - WPS "Madan" – Technical design with tender documentation NEK 1998г.
14 Gorna Arda hydropower project - WPS "Ardino" – Technical design with tender documentation NEK 1998г.
15 Gorna Arda hydropower project – shifting of the main road Smolyan - Kardzhali in the area of dam "Madan" NEK 1998г.
16 Gorna Arda hydropower project - WPS "Madan" road III-867 Rudozem - Kardzhali, technical design and tender documentation for a bridge and a tunnel at the village of Varbina and increase of the sum NEK 2000г.
17 Gorna Arda hydropower project - WPS "Sarnitsa" – Technical design with tender documentation NEK 1998г.
18 Gorna Arda hydropower project - technical design for technological and operating roads for WPS "Ardino" and WPS "Sarnitsa" NEK 1998г.
19 Gorna Arda hydropower project - WPS "Madan" – Technical design with tender documentation NEK 1998г.-2001г.
20 "Work design for the reinforcement of counter-wall "Rozov Kladenec" and "Soil Design" NEK - EAD - Enterprise "Dams and cascades" 2001г.
21 Cascade “Dospat – Vacha" Additional water supply in the river valley of Dospat dam – Collective Derivation “Osina" Water Capture No 7 – work design and designer supervision; NEK 1997-2000
22 HPP "Kunino" at Iskar River – Surveys under article 66 from the Water Law "Sofia-Centre" EOOD  
23 Collective Derivation "Dzherman – Skakavitsa" – work design and designer supervision during the construction process. NEK 1996 - 1999
24 "Beli Iskar" Dam Reconstrucion; Diversion euqipment – technical design; Temporary roads in the are of the dam wall; Calendar plan – schedule for the execution of the types of works for the reconstruction of the dam wall Sofiyska Voda 1996-1998
25 HPP "Kunino" at Iskar River – Surveys under article 66 from the Water Law "Sofia-Centre" EOOD  
26 Cascade “Belmeken – Sestrimo" – Collective Derivation “Granchar". Reconstruction of the derivation in the area of exit tunnel "Beli Iskar" and water capture 21 for the needs of additional drinking water supply of Sofia from Rila NEK 1994-1996
27 Cascade “Dospat – Vacha"- WPS “Tsankov Kamak" pre-design studies; development of variant solutions for the underground equipment – pressure tunnels and cross-tunnels with Ø= 3,00 – 6,00 м. NEK 1994-1996
28 Work design dam "Studena" MRDPW (Ministry of Construction Works) 1986 г.
29 Dam wall "Borovitsa" documentation of excavations and designer supervision for the construction process Ministry of Construction Works 1986-1995г
30 "Draginovo" Dam, rock-fill wall – Preliminary design Ministry of Energy 1984-1995
31 "Galabovo" Dam earth-fill homogeny wall – Preliminary design Ministry of Energy 1984-1990
32 "Chervena reka" Dam – reconstruction (for potable water supply of TPP "Maritsa East ") – additional construction of 6 m Ministry of Energy 1984-1990
33 "Byal cladenets" Dam – Construction of a permanent barrage structure for the new canal NEK 1982-1989
34 Counter-wall "Ovchi kladenets" – Strengthening of the slopes NEK 1982-1989
35 Water Power System "Yovkovtsi", "Veliko Tarnovo" derivation and "Oryahovitsa" derivation Regional People's Council Veliko Tarnovo 1982-1989
36 "Draginovo" Dam, "Dolene" Dam – guiding of engineering and geological surveys of "Draginovo" Dam with height Н = 75 m and "Dolene" Dam of the "Mesta" cascade with height Н = 55 m NEK 1982 -1985г.
37 "Lakatnik" Dam with height Н = 75 m, concrete wall on rock base; Waste water collection place "Rudozem" Н = 30 m, earth-fill wall on rock base; NEK 1972-1980г.
38 "Dospat – Vacha" Cascade – Main pressure derivation "Devin" NEK 1972 - 1982
39 "Belmeken" Dam – 98 m rock-fill wall, 725 m of length will central clay core. Slippage resistance of slopes, hydraulic and static calculations of the following structures: main (bottom) discharger, spillway and derivation tunnel. Ministry of Energy Година на завършване 1975.
40 "Stankovi baraki" Dam with 40 m of height, 82 m of length, bottom изравнител of the "Belmeken" Dam, rock-fill wall with central clay core. Static and hydraulic calculations of the structures: main (bottom) discharger, spillway and derivation tunnel. Ministry of Energy 1970-1975
41 "Chaira" Dam, 88 m of height, 288 m of length, concrete gravitation wall. The Project consists of spillway, main (bottom) discharger and derivation tunnel. Ministry of Energy 1970-1999
42 Chemical plant "Devnya" – Waste waters collection places; participation in an examination of the strength of the wall slopes, static and hydraulic calculations of underground manifolds. Control and measurement system. Ministry of Chemistry and Metallurgy 1970-1980
43 TPP "Maritsa East" 1, 2 and 3 – Waste waters collection places; participation in an examination of the strength of the wall slopes, static and hydraulic calculations of underground manifolds. Control and measurement system. Ministry of Energy 1970-1995
44 TPP "Bobov dol" – Author's supervision of Waste waters collection places Ministry of Energy 1970-1995
45 "Yasna polyana" Dam – subsites: spillway and rock quarry; State Navigation Inspectorate "Water supply of Black Sea Shore" 1968 - 1970
46 "Yasna polyana" Dam – "Yasna polyana" derivation; State Navigation Inspectorate "Water supply of Black Sea Shore" 1968 - 1970
47 WPP "Krichim" – collection derivation "Churinsko dere" pressure-less canals, sag pipes – Work Designs; Ministry of Energy 1968 - 1970
48 Water power system "Yovkovtsi" pressure derivations "Veliko Tarnovo", "Oryahovitsa" – Work designs – derivation concrete and steel pipelines, crossing s of rivers, gullies, roads and railroads; Author's supervision durong the construction works; Окръжен народен съвет
( ОНС) Велико Търново
1968 - 1970
49 "Pirinska Bistritsa" cascade and "Sandanska Bistritsa" cascade, Waste waters collection places "Medet" and "Chelopech". Engineering and geological surveys and building of 5 dams of "Pirinska Bistritsa" cascade and "Sandanska Bistritsa" cascade and Waste waters collection places "Medet" and "Chelopech". Bottom equalizers with height Н = 20-25 m. WPP power = 15-20 MW/; Н = 105 m (inwash) Н = 20 m (embankment) Н = 30 m (embankment) Ministry of Energy 1968г.
50/td> "Anton Ivanovtsi" Dam and "Krichim" Dam of the "Vacha" cascade: engineering and geological surveys and building of the "Anton Ivanovtsi" Dam and "Krichim" Dam of the "Vacha" cascade with heights Н = 105 m and Н = 145 m, respectively, concrete walls on rock base. Ministry of Energy 1961-1964Г.
51 "Belmeken" Dam and "Rozov kladenets" Dam (Realization of Control and Measurement system): Н = 73 m (embankment); Н = 35 m (embankment) Ministry of Energy  
52 "Gorna Arda" Cascade, Water power system "Sarnitsa" (Dam and WPP) Н = 105 m (concrete) Ministry of Energy  
53 "Anton Ivanovtsi" Dam, "Krichim" Dam, "Kardzhali" Dam; "Chaira" Dam, "Vasil Kolarov" Dam; "Batak" Dam. Processing of the results of engineering and geological surveys related to the rehabilitation following the Terms of reference of the World Bank and International Monetary Fund + Engineering and geological surveys related to opencast mines and slumps - "Beli Bryag" Mine Ministry of Energy  
54 Dams "Saf – Saf" and "El hakika": Detailed surveys, technical design, tender documentation Ministry of the Equipment, Algeria 1996-1997
55 "Meksena" Dam: Construction drawings Ministry of the Equipment, Algeria 1996
56 "Bogus" Dam: Detailed surveys, technical design, tender documentation Ministry of the Equipment, Algeria 1995-1996
57 Water power systen "El Hakika": technical design for the derivation tunnel – Height / Width = 4.0 / 4.0 m Algeria 1994-1996
58 WPP "7th of April": Construction drawings Ministry of the Irrigation, Syria 1993-1994
59 Purification Plants "Sebdol", "Lagut", "Remchi" and "Marsat bin Mhidi": Technical designs and tender documentation Ministry of the Equipment, Algeria 1992-1994
60 Dams "Posfa" and "Kisir": Detailed surveys Ministry of the Equipment, Algeria 1992-1994
61 WPPs "Moa" nd "Twuiniku": Work draqwings of the machine and electrical part Energoimport, Cuba 1988-1989
62 WPP "Abrash": Preliminary design, technical design and tender documentation Ministry of the Irrigation, Syria 1988-1989
63 Engineering project – 6 Water power plants Energoimport, Cuba 1986
64 Automated pump, 120 pieces: Preliminary design and work drawings Ministry of the Irrigation, Commonwealth of the Independent States 1985-1988
65 Irrigation system "Akar": Preliminary design and work drawings Ministry of the Irrigation, Commonwealth of the Independent States 1985-1988
66 "Snubar" Dam: Geological surveys Ministry of the Irrigation, Syria 1985
67 WPP "Snubar", 2 pcs.: Preliminary design, work design and tender documentation Ministry of the Irrigation, Syria 1985-1987
68 Water-technical plants upon Tatlang river: technical and economic documentation and technical design Ministry of Industry, Laos 1985-1986
69 "Moamba-Маjог" Dam: Surveys; Н = 40 m, L = 60 km, rock-fill dam wall; preparation of hydro-geological report with graphical attachments Ministry of the Agriculture, Mozambique 1982 -1985г.
70 System in water collection zone of the Habur river: technical and economic documentation, technical design and tender documentation Ministry of the Agriculture, Syria 1982-1984
71 Hydropower complex upon Ye-Ye river: Preliminary design and technical design Nicaraguan Institute of Power Energy, Nicaragua 1982-1983
72 TPP "Derna 2" and "Tobruk 2": Consultancy services and site supervision Secretariat for Electrification, Benghazi, Libya 1981-1986
73 "Wadi Lybda " Dam, 29 m of height, length of 700 m; earth-fill dam wall with vertical filters. Participation in preparation of the work design for the dam wall, main discharger, water intake tower, closing equipment chamber. System for control and measuring. Work drawings for 11 small barrages of gabions Agrocomplect, Libya 1980-1983
74 Four power substations: surveys, preliminary designs and work drawings Ministry of the Industry and Power Energy, Mozambique 1979-1981
75 "El Fakia" Dam (Wisert); Supervision of the construction works Ministry of the Waters, Land usage and Environment, Algeria 1979-1981
76 "Mamposton", "Pedroso", “Layaya", "Maurin", Los Palacios" – survey and building of dams in Cuba, with heights of 20 to 50 m, earth-fill walls. Ministry of the Agriculture – Water resources, Cuba 1968-1972г.

Енергопроект АД

ENERGOPROEKT JSC
51, James Boucher Blvd., 1407 Sofia, Bulgaria
Phone. +359 2 960 78 00

VAT № BG 831367237
UIC 831367237

Board of Directors:
Nikola Stoilov
Jivko Jeliazkov
Magdalena Ilkova

Financial Director:
Rusko Kuzmov